ENERGY | SOLAR POWER

NamPower Plans N$1.3 Billion Solar Plant Near Omaruru By 2028

The 80 MW solar project is expected to begin construction in 2028, with the utility targeting commercial operations in 2029.

NamPower plans to construct an 80 MW solar power plant near Omaruru, with commercial operations targeted for 2029.
NamPower plans to construct an 80 MW solar power plant near Omaruru, with commercial operations targeted for 2029. Photo: Contributed

NamPower plans to build an 80-megawatt (MW) solar power plant near Omaruru at an estimated cost of N$1.3 billion, with construction expected to start in the first quarter of 2028.

According to project information published on its website, NamPower said the Omburu Solar PV II project is expected to generate approximately 240 gigawatt-hours (GWh) of electricity annually, with commercial operations targeted for the second quarter of 2029.

The utility stated that the project is currently in its establishment phase, with activities focused on engineering and environmental requirements ahead of construction. NamPower indicated that procurement processes for an engineering consultant and an environmental practitioner had closed, with the evaluation of bids under way.

NamPower said it expects to appoint an environmental practitioner in October 2026 and an engineering consultant in November 2026. The appointments will support the detailed engineering design, environmental assessments and preparation of documents required for construction.

The utility further stated that it plans to appoint a construction contractor in the fourth quarter of 2027, while procurement of major solar equipment is also scheduled for the same period. Construction is expected to commence in the first quarter of 2028.

On environmental requirements, NamPower said the project requires a full Environmental and Social Impact Assessment (ESIA) and an amended Environmental Clearance Certificate (ECC), with both targeted for completion in the second quarter of 2027. The utility also plans to submit its electricity generation licence application to the Electricity Control Board (ECB) in the third quarter of 2027.

NamPower stated that the plant will be developed on its 300-hectare property near the existing Omburu Substation, approximately 10 kilometres south-east of Omaruru, with about 258 hectares indicated available for the proposed development after accounting for the existing 20 MW Omburu Solar PV Power Station.

The project fact sheet further states that the plant will connect to the national grid through the existing Omburu Substation using the 220-kilovolt (kV) transmission network. NamPower confirmed that it had already received and accepted the transmission connection offer.

It's also reported that the plant will be designed to accommodate future battery energy storage integration, with a proposed capacity of approximately 64 MW and 128 megawatt-hours (MWh). However, NamPower noted that the installation will depend on technical and economic viability.

On financing, NamPower stated that the project is planned to be funded through its balance sheet, although corporate borrowing from institutional lenders may also be considered, however the financing arrangements are still under evaluation.

In addition, NamPower said the project is intended to support the country's efforts to increase domestic electricity generation, reduce reliance on imported power and contribute towards the National Integrated Resource Plan's target of achieving 80% electricity self-sufficiency by 2028.