National Planning Commission Highlights Gaps in Planning Government-Funded Projects

Namibia's development spending is falling behind because government institutions are allocating money to projects before completing the necessary preparatory work, while procurement delays, limited technical capacity and weak project management continue to obstruct implementation.

National Planning Commission Highlights Gaps in Planning Government-Funded Projects
Photo: Photo Contributed

Namibia's development spending is falling behind because government institutions are allocating money to projects before completing the necessary preparatory work, while procurement delays, limited technical capacity and weak project management continue to obstruct implementation.

The National Planning Commission (NPC) has acknowledged these challenges following questions from Business Pulse 360° about why government had executed only 42% of its development budget by the mid-year point of the 2026/27 financial year, compared with 53% for operational expenditure.

In a written response, Maria Kandjungu, Senior Public Relations Officer in the Office of the Executive Director at the NPC, explained that development spending is more difficult to execute because infrastructure and capital projects involve lengthy and complex implementation processes.

However, one of the most revealing explanations in her response was that some projects receive government funding before the necessary preparatory work has been completed.

According to Kandjungu, "Projects are sometimes allocated funding before all the necessary preparatory work has been completed, resulting in delays in commencing implementation."

This raises questions about how government institutions prepare and assess projects before including them in the national budget, particularly when funding is approved for initiatives that may not yet be ready for implementation.

Kandjungu identified several other factors contributing to the slow execution of development expenditure, including lengthy procurement processes, legal disputes and court challenges. Land acquisition difficulties, environmental approvals and unresolved community concerns also affect project timelines.

She further pointed to limited technical and institutional capacity at national, regional and local authority levels, which affects the ability of government institutions to implement, manage and monitor projects effectively.

Another challenge, according to the NPC, is that some institutions attempt to undertake too many projects simultaneously, spreading available financial and human resources across multiple initiatives.

The explanation comes at a time when the difference between operational and development spending is becoming an important concern for public investment and service delivery.

While operational expenditure covers recurring government costs such as salaries, pensions, utilities, fuel, rent and social transfers, development expenditure finances long-term investments in infrastructure, including roads, schools, hospitals, water and sanitation systems, housing and other public facilities.

Kandjungu explained that operational spending tends to be more predictable because it covers the day-to-day running of government institutions. She also stressed that operational expenditure enables the delivery of development projects.

However, slow development spending carries consequences beyond the failure to implement projects according to schedule.

Kandjungu warned that delays can make infrastructure projects more expensive because construction materials, labour and other inputs increase in price over time.

"Project delays often result in increased costs," she said, adding that unfinished projects continue to tie up public resources and may require additional allocations in subsequent financial years.

This creates further pressure on government finances and limits the resources available for other priority projects.

The implications also extend to the implementation of the Sixth National Development Plan (NDP6). The NPC acknowledged that low development-budget execution slows progress towards national development objectives, leaving intended beneficiaries waiting longer for essential infrastructure and services.

"Low development budget execution translates into slower development and delayed service delivery," Kandjungu said.

To address the problem, she explained that the NPC works with the Ministry of Finance to engage Offices, Ministries and Agencies (OMAs), assess implementation progress and identify bottlenecks requiring corrective action.

The Commission may recommend redirecting resources from projects experiencing slow implementation to those that are ready and demonstrate better implementation capacity.

Kandjungu also disclosed that the NPC has strengthened its Monitoring and Evaluation framework through the development of an online system intended to track development-project implementation in real time.

She said the system would move the monitoring process from a paper-based approach to an online platform.

Under the existing arrangements, government institutions submit project execution plans at the beginning of each quarter, outlining activities, costs, implementation timelines and expected outputs. Progress reports are submitted at the end of each quarter, detailing expenditure, physical implementation and challenges affecting delivery.

The NPC also conducts field monitoring visits, stakeholder consultations and performance review meetings to verify reported progress.

Where implementation falls behind, the Commission engages the respective institutions and recommends measures that include addressing procurement bottlenecks, improving project planning and management, strengthening institutional capacity and accelerating outstanding approvals.

The 42% development-budget execution rate therefore raises a broader question about whether government is adequately preparing projects before allocating public money and whether existing monitoring mechanisms are sufficient to ensure that approved development plans translate into completed infrastructure.

For Namibia, the challenge is no longer simply about how much money is allocated to development, but whether government institutions can effectively turn those allocations into projects that improve people's lives.